Project timeline

NEW - now installed on site is a time lapse camera tracking the progress of the build. You can zoom in and check out shots from days past by clicking on the link below:

New Marlowe Theatre time lapse photography camera

2008


Planning Permission granted.

2009

March

Demolition of the Friars Motors Centre.

Archaeological investigations carried out underneath Friars site.

Closure of the Marlowe Theatre on 22 March 2009.

April

Contractor appointed with a start on site date of end of April.

Demolition of the existing theatre structure commences.

April - December

Construction work progresses.

Please note - monthly updates will be provided during the construction process.

2010

Construction work progresses.

Fundraising Campaign continues.

'Marlowe in Motion' performances and events held across the district.

2011

Completion of construction work.

Specialist fit out of the new theatre.

Training and 'soft' opening.

The new Marlowe opens in September 2011.



Stay up to date

Sign up to our newsletter to be kept informed of all the latest developments

Register

Current Marlowe Shows

The Marlowe Theatre building may have closed but you can still enjoy top shows in a number of different venues.

Click Here to Book Tickets and Find Out More

BOX OFFICE: 01227 787787